Installation of A/C in the remainder of spaces at MS and HSW.
Commissioning of the A/C system is planned for late Spring/Summer 2028.
Work at MS includes paving, roof and boiler replacement, generator replacement, electrical upgrade, stage rigging, PA system upgrade, and asbestos abatement - flooring.
Work at HSW includes paving, boiler replacement, electrical distribution upgrade, security upgrades, stage rigging, and asbestos abatement - flooring.
Includes work at Arongen/Shatekon, Chango, Karigon/Orenda, Okte, Skano/Tesago, and High School East (HSE).
HSE work includes roofs, HVAC updates, IT switchgear, piping replacement in select areas, auditorium house lights, stage rigging, PA system upgrade, toilet room upgrades, asbestos abatement-flooring, and conversion of locker room space to Team Rooms and an Entertainment Production Studio.
Other work includes CTE/Robotics Space, Athletic Fields upgrade, select classroom renovation, and Transportation infrastructure (EV buses, paving, generator).
$26.5 Million Capital Project Approved by Voters 2021